Filed under: Construction photos

Gallery: Plumbing, Electrical & HVAC Rough-In

Leave a Comment February 26, 2010

Gallery: Siding Installation

We are moving ahead to install the siding of our house!  The house will look a lot nicer (& more like the rendering) after siding is installed.  We are doing open rain screen on many areas of the house.  On areas where there is an open rain screen, we will install 2 layers of vapor shields (orange paper + black paper as you will see in the pictures).  On areas where there is no open rain screen, only the orange layer vapor shield is needed. 

Because of our contemporary design, we are using 3 different types of siding on the house: Cedar wood (with stains/coating), fiber cement boards (olive color) and aluminum panels (white color). 

Leave a Comment February 25, 2010

Gallery: Rainwater tank installation

Our 1,700 gallon rain water tank has arrived and finally ready to be installed underground!  Below you will see pictures of our tank, tank embedded into our backyard and also after the area has been backfilled. 

Leave a Comment January 30, 2010

Gallery: Windows and Skylights Installation

Leave a Comment January 15, 2010

Milestone: Framing completed!

After a few weeks of hard work, framing is finally complete!  Our house framing consists of structural insulated panels (SIPs) for walls and roof, combined with some portion with traditional stick framing. 

Siding will start soon and I’m sure the house will look a lot nicer (and more like the original rendering) when siding is complete.  Stay tuned for more pictures later!

Leave a Comment January 14, 2010

Gallery: Framing & SIPS

SIPS walls were put up first before stick frames.  We started tilting up the 1st floor panels first, and then fill in the stick framing around the garage and some of the north and south facing walls (where there are many windows and didn’t make sense to use SIPS).  The floor joists and floor sheathing came after that.  Then the 2nd floor SIPS panels were delivered and installed first before the stick framing for the 2nd floor.  All SIPS panels for walls were tilted by hands, with 2-3 people.  Not using any cranes until the roof panels come in.

               

Leave a Comment December 21, 2009

Gallery: Concrete Slab

These are the pictures taken during the pouring of our concrete slab on the main floor during last week of November, 2009. 

Radiant Floor Concrete Framing 083Radiant Floor Concrete Framing 086Radiant Floor Concrete Framing 089Radiant Floor Concrete Framing 090Radiant Floor Concrete Framing 091Radiant Floor Concrete Framing 098Radiant Floor Concrete Framing 100Radiant Floor Concrete Framing 105Radiant Floor Concrete Framing 116Radiant Floor Concrete Framing 118Radiant Floor Concrete Framing 121Radiant Floor Concrete Framing 127Radiant Floor Concrete Framing 134

Leave a Comment November 30, 2009

Gallery: Under slab Insulation & Radiant Heating

Before pouring the concrete slab, installation of 3″ rigid foam insualtion, 10 mil vapor barrier, 6×6 metal mesh, and hydronic PEX tubing for the radiant heating.  Notice the chamfered foam we put at the perimeter of the slabs, because we are using finished concrete floor throughout the 1st floor and we want to hide the foam from being exposed.

Radiant Floor Concrete Framing 045 Radiant Floor Concrete Framing 047 Radiant Floor Concrete Framing 048 Radiant Floor Concrete Framing 042 Radiant Floor Concrete Framing 060 Radiant Floor Concrete Framing 054 Radiant Floor Concrete Framing 056Radiant Floor Concrete Framing 063 Radiant Floor Concrete Framing 066 Radiant Floor Concrete Framing 068 Radiant Floor Concrete Framing 067

Leave a Comment November 20, 2009

Gallery: Underground Work

These are the pictures of the underground work during 1st week of November, 2009.

Radiant Floor Concrete Framing 005Radiant Floor Concrete Framing 008Radiant Floor Concrete Framing 012Radiant Floor Concrete Framing 013Radiant Floor Concrete Framing 018Radiant Floor Concrete Framing 019Radiant Floor Concrete Framing 031Radiant Floor Concrete Framing 037

Leave a Comment November 6, 2009

Gallery: Footing drains, Backfill & Infill

These are the pictures taken when we were installing the footing drains as well as during backfilling and infilling of our house. 

H-House footing drains infill backfill 002H-House footing drains infill backfill 004H-House footing drains infill backfill 011H-House footing drains infill backfill 020H-House footing drains infill backfill 023H-House footing drains infill backfill 032H-House footing drains infill backfill 036H-House footing drains infill backfill 038H-House footing drains infill backfill 046H-House footing drains infill backfill 048H-House footing drains infill backfill 052H-House footing drains infill backfill 055

Leave a Comment October 23, 2009

Previous page


Blog Topics

About us

Green concept home is a prototypical house designed by modus v studio architects. For more information on the company, please visit

www.modusvstudio.com

Newsletter

Please leave us your contact information if you would like to stay in touch with us.